Yeah, don’t hold me to this – I can’t actually gaurantee the timeline on this, but this is the breakdown of my upcoming layout work. The order of tasks is correct, but beyond that, timing is anyone’s guess.
- Table construction – completed on 11/10/2019 (minus drop panel for river area)
- Drop-panel for river area – completed on 11/16/2019
- Foam base for sub-roadbed – to be completed by 12/01/2019
- Spackle / fill and smoothing of sub-roadbed – 12/22/2019
- Wiring terminal blocks – 12/31/2019